Starting Tuesday, May 26, construction crews will be out on Front Street making some much-needed repairs. Work will take place weekdays from 7 a.m. to 5 p.m.
The Game Plan:
May 26 – 29: Crews will focus on repairing stormwater catch basins and replacing the concrete “dance floor” by the gazebo.
May 30 – 31 (Weekend): No construction! Front Street will be fully open for the weekend.
June 1 – 3: Demolition and replacement of the crosswalk at 8th & Front Street, plus minor asphalt repairs.
June 4 – 5: Seal coating Front Street (8th to 9th will be sealed on June 4).
Notes: Miscellaneous sidewalk repairs will also happen throughout the two weeks with minimal interruption to businesses and out-of-town guests. The project timeline and seal coating are weather-dependent.
Crews will be working directly in the roadway. Please respect all traffic cones and barricades to keep both yourself and our workers safe!
Stay up to date! For schedule adjustments and project details, visit our Project Tracker: cityofleavenworth.com/projects.