Last Updated: June 21, 2024

PROJECT TYPE:

Facility Improvements

PROJECT VALUE:

$1,197,874

PROJECT SCHEDULE:

Bid Ad: February 28, 2024
Bid Opening: March 20, 2024 at 11am PST
Bid Rejection: April 9, 2024
Rebid Award:
June 11, 2024
Construction: Summer 2024 – Spring 2025


PROJECT UPDATES:

July 25, 2024 Update – Starting Monday, August 5 the Front Street Restroom facility will be CLOSED. The contractor for the City of Leavenworth is expected to begin onsite mobilization, including the installation of construction fencing around the worksite.

June 11, 2024 Update – City Council accepted the bid from Cascade Central Construction, LLC, for construction of the project. Construction is anticipated to being this summer.

April 20, 2024 Update – One (1) bid in the amount of $2,034,000, was received from Cascade Central Construction, LLC, on 3/20/2024. During the regular City Council meeting on 4/9/2024, the Council rejected all bids received. Bid rejection will delay the previously anticipated timeline for project construction.

March 5, 2024 Update – This project is currently out to bid. Invitation to Bid – Front Street Park Restrooms & Stairway Expansion – City of Leavenworth

Timeline

Bidding

March 2024

Construction Begins (Tentative)

To Be Determined

Construction Complete (Tentative)

To Be Determined
CONTACT INFORMATION:

Andi Zontek-Backstrum, PE
CIP Manager/Deputy Public Works Director
Email: [email protected]
Phone: (509) 548-5275 ext. 134

OTHER INFORMATION:

Public Outreach Flyer March 2024

 

The design of the Front Street Park Restroom and Stairway Expansion project is complete! Construction is anticipated to begin in Spring 2024 and construction is anticipated to be completed in early 2025. A more specific timeline will be provided once a contractor is under contract.

Generally, the project consists of the following:

  • Switching the locations of the male and female restrooms
  • Expanding the female restroom to have 7 stalls and 5 sinks
  • Add a family/gender-neutral single stall restroom
  • Reconstructing covered concrete stairs between Front St and US 2
  • Covering the area above the restroom

This construction project is anticipated to cause temporary disruptions to nearby businesses. Anticipated disruptions include but are not necessarily limited to noise, dust, and changes to pedestrian or vehicle traffic flows. Access will be maintained to all businesses during the project and with the existing stairway between US 2 and Front Street closed, the City will provide signage to route pedestrians to 9th Street between US 2 and Front Street.

Frequently Asked Questions:

 

Will the restrooms be open during construction?
Restrooms will be closed for the duration of the project.

 

What are the anticipated days / hours of construction?
Work will take place Monday – Thursday between the hours of 7am – 6pm.

 

What other public restroom facilities will be available?
In addition to the public restroom facility on 8th Street, the City will provide portable toilets.

 

Will the Front Street stair and restroom project be delayed since bids apparently came in too high?
Yes, the recent bid rejection will delay the previously anticipated timeline for the project.

 