Last Updated: June 21, 2024

PROJECT TYPE:

Street Improvements

PROJECT VALUE:

$1,731,500

PROJECT SCHEDULE:

Bid Opening: April 3, 2024 at 2:00 p.m. PST
Bid / Contract Award: May 28, 2024
Construction: Summer thru Fall 2024 (tentative)


PROJECT UPDATES:

September 17, 2024 Update – Scrub sealing officially started this morning. Click here for a revised map of the streets scheduled for scrub seal (NOTE: Locations/extents of the work are approximate and subject to change. Daily street schedules are approximate and subject change).

August 30, 2024 Update – Asphalt work (patching and preleveling) is planned to start soon. Outlined in a daily, color-coded sequence, click here for a map of the streets scheduled for scrub seal (NOTE: Locations/extents of the work are approximate and subject to change. Daily street schedules are approximate and subject change).

August 19, 2024 Update – Asphalt work (patching and preleveling) is planned to start the week of 8/26 (the start date is subject to change). This work should be minimally disruptive to general traffic flows. Scrub seal work is planned to start the week of 9/3 and continue the week of 9/9 (the start date is subject to change). During scrub seal work, impacts include no on-street parking for multiple days while the work is being completed.

June 9, 2024 Update – Work is anticipated to begin this June (the start date is subject to change). During construction, impacts include no on-street parking for multiple days while the work is being completed.

May 28, 2024 Update – City Council awarded the project to One Way Trigger, LLC.

April 20, 2024 Update – On 4/3/2024, the City received four (4) bids, ranging from $1,178,870.00 to $1,643,156.00. The engineer’s estimate of probable construction costs was $1,731,500.00. Bid  / Contract Award is currently on the agenda for the regular City Council meeting on 4/23/2024.

March 20, 2024 Update – This project is currently out to bid. Learn more at Bidding.

CONTACT INFORMATION:

Andi Zontek-Backstrum, PE
Deputy Public Works Director
Email: [email protected]
Phone: (509) 548-5275 ext. 134

OTHER INFORMATION:

REVISED Daily Scrub Seal Map from Contractor (One Way Trigger)

DRAFT Door Hanger from Contractor (One Way Trigger)

Scrub Seal Postcard Mailer (June 2024)

To learn more about the scrub seal pavement treatment process, visit https://www.youtube.com/watch?v=m50z5F_vF4c.

 

The 2024 Scrub Seal Project, is a significant initiative aimed at preserving our City’s roadways. The scrub seal method involves applying an asphalt emulsion and crushed rock to the roadway. This cost-effective method of pavement preservation fills existing roadway cracks and provides protection to the existing roadway surfacing. The project is part of our ongoing commitment to maintaining and improving the City’s infrastructure.

  • Project Highlights:
    • It is anticipated that some sections of the scrub seal will fail. TIB is testing the limits of this treatment in some locations in Leavenworth’s roadway network system.
    • Application of the scrub seal is a “catch up” method which will be followed with implementation of a pavement preservation program.
    • This scrub seal treatment will not improve the “ride” of the road.
    • Overall, design life for a scrub seal treatment is ~5-8 years.

This project is 90% funded by the Washington State Transportation Improvement Board (TIB).

Frequently Asked Questions:

 

I am a resident. How will this project impact me?
The impact to residents includes no on-street parking on multiple days to complete the work (e.g., scrub seal, fog seal, striping).

 